5 × 400kW Backup Power Solution For Drainage Pump Station– Taicang, China

e1bcb098-65e0-4a5f-b43c-5e5dd369a030

Project Background

Taicang is located in the Yangtze River Delta's low-lying plains, where heavy rainfall and river backflow pose frequent flooding risks during monsoon and typhoon seasons. 

The Taicang Inner Lake Pumping Station required a high-reliability diesel generator backup system to guarantee uninterrupted power supply during grid outages. Ensuring pump station operation in such emergencies is critical for urban flood protection and public safety.

Project Challenges

Drainage operations require seamless, uninterrupted power, especially during storm surges or citywide blackouts. 


The station uses five 400kW diesel generator sets. These units must start, stop, and run in parallel, balancing loads based on real-time pump demand. 


Located near water bodies and low-lying terrain, the generators face high humidity, corrosion risks, and potential floodwater exposure.

bea53e43-8d61-4833-82c9-6beca30f4f97
4bb6f23a-bf15-4a9a-bbe4-1a8c937aeafe
1280X1280 (5)

Haifeng Engineering Solution

Parameter Specification
Power Output 5 × 400kW Prime Rated
Engine Cummins KTA19-G3A
Alternator Stamford HCI544D
Control System Intelligent Paralleling Module (DSE/SmartGen)
Voltage/Frequency 400/230V, 50Hz, 3-phase
Fuel Tank 1200L base tank per unit
Structure Silent, corrosion-resistant enclosure with rainproof design
Operation Mode Grid-auto switch, parallel operation, load sharing, redundancy rotation

Testimonials

"The Taicang Inner Lake Drainage Pump Station relies on continuous power to protect the city during heavy rains and floods. With Haifeng Power’s 5×400kW silent diesel generator sets, we now have full confidence that our pumps will never stop, even if the grid fails during extreme weather. The seamless parallel system, automatic load sharing, and extended fuel autonomy have ensured reliable, uninterrupted operation. This solution has become an essential safeguard for the city’s flood prevention efforts."

1516666880155

Guangli Zhang
Station Manager

"Haifeng Power provided not just equipment, but a complete and intelligent backup power solution tailored to our unique needs. The anti-corrosion design, soundproof enclosures, and smart synchronization system all proved invaluable in our humid, flood-prone environment. The system has already operated flawlessly during emergency drills, meeting both environmental and safety requirements. Thanks to Haifeng Power, our wastewater treatment and drainage operations can continue with stability and efficiency, protecting both the community and the environment."